April 2022 Update
Bogard Construction continues to make progress on this project. Phase One includes the clinics for Dientes and Santa Cruz Community Health (SCCH). For the Dientes dental clinic exterior, the stucco and paint are complete and lighting and fire alarm work is ongoing. Inside, painting, ceiling and light fixture installation, and bathroom tiling is continuing. For SCCH, roofing continues in earnest, the second-floor walls are nearly all framed, and stucco work will begin soon. Inside, framing and plumbing are in progress. Phase Two includes four apartment buildings for MidPen Housing. Exciting news, foundation work has begun!
The image below updates every 10 minutes by refreshing your screen.
1500 Capitola Rd (Santa Cruz, CA)